Case Studies
Client: Wilton Centre Laboratories – Redcar - Middlesbrough
Benefits:
• Energy savings = 3.4m kWhr/pa
• Energy cost savings = £205,000
• Emissions reduction = 1,700 te CO2
• Simple pay back typically = 1. 3 >1.7 years
Facility: Large laboratory Facility spread over 5 blocks - originally designed as ICI’s R & D Facility
Issue: Old HVAC plant serving a very large number of face & bypass fume cupboards
Brief: Reduce energy demand without compromising on operator safety
Solution:
• Upgrade supply units with control & filtration upgrades
• Retrofit VAV to the existing fume cupboards
• Install pressure controllers to each laboratory
• Initiate fume cupboard diversity into each laboratory
• Strip out all the primary extract fans & upgrade secondary fans with VSD’s
• Installation of energy monitoring units to verify savings & act as MM&T capability
Conclusion: EECO2 – Phased upgrade over 3 years = carried out complete system redesign, scope & bid proposal on Clients behalf, laboratory user interphase & programming. Provided Project Management for Contractors – delivered to budget, on time with 0 accidents or incidents
Site Energy Manager Comments:
We have just read the electricity meters in R Block for April, & I thought you might be interested to see the effect of the ventilation modifications which we have carried out. Basically, you can see that a monthly figure of around 120 MWhr has reduced to around 70 MWhr, which is a very significant reduction.
When we also compare total steam use for the whole Wilton Centre for 2009 with 2008, where we see a reduction of 9.5%, & some of this will be due to the similar work we did in T Block.
It is our intention to now carry out similar modifications in D, N & E Blocks.
Richard Short
Site Utilities Manager

Client: GSK – Consumer Health Supply Division – Buenos Aires - Argentina
Benefits:
• Energy savings = 1.5m kWhr/pa
• Energy cost savings = £58,000
• Emissions reduction = 686 te CO2
• Simple pay back = 11 months
Facility: Effervescent Sachets Manufacturing Area – low relative humidity required
Issue: Very high energy demand driven by original HVAC design & unable to meet Product critical conditions during summer months
Brief: Reduce energy demand without compromising on product quality or Compliance
Solution:
Solution:
• Reduce existing air change rates
• Reduce existing fresh air volume
• Install new VSD’s to the supply air fans
• Replace the existing supply air diffusers to improve air distribution
• Re-commission & balance the complete manufacturing areas HVAC system
• Supported upgrade of BMS system, installation of VSD’s
• Maintenance upgrade of filtration & control valve replacement
• Completed product risk assessments, Engineering Change Control documentation & all required Regulatory documentation covering the changes
Conclusion: EECO2 supported HVAC design review, recommissioned HVAC system & supported BMS & HVAC upgrade also design of new supply air diffusers
Site Director commented:
The savings delivered during Phase 1 has exceeded our expectations & the quality Team have supported the risk based approach used to deliver the savings. We now move on to Phase 2 upgrade which is much more demanding but the confidence & structure knowledge we gained during phase 1 we help us deliver our target for 2011

Client: GSK – GMS Division – Quality Road & Jurong sites - Singapore
Benefits:
• Energy savings delivered = 2.2m kWhr/pa
• Energy cost savings = S$347,000
• Emissions reduction = 985 te CO2
• Simple pay back = 1.3 years
• Further energy savings identified = 2.5m kWhr/pa
Facility: Pharma Manufacturing & laboratories
Issue: Very high energy demand driven by original HVAC design & layout
Brief: Reduce energy demand without compromising on Compliance or Laboratory safety
Solution:
• Reduce existing air change rates
• Reduce existing fresh air volume
• Improve plant operational maintenance
• Optimise BMS system
• Recommended upgrading laboratory fume cupboards to VAV
• Recommended upgrade & control of warehousing Facilities
Conclusion: EECO2 supported HVAC design review, project scoped out & managed local test & balance & BMS Contractors to complete project – project successfully completed also produced a prioritised Action Plan to implement further savings

Client: GSK – Consumer Health Supply Division – Memphis – Tennessee
Actual Verified Benefits:
• Energy savings delivered = 1.95m kWhr/pa
• Energy cost savings = $135,000
• Emissions reduction = 917 te CO2
• Simple pay back = 1.5 years
• Capital cost avoidance from not replacing
Retained Sample Store HVAC = $35,000
Facility: CME Warehouse - temperature & humidity controlled storage of regulated product, also include the HVAC system in the Retained Sample Store (existing R22 plant obsolete)
Issue: Very high energy demand driven by original HVAC design & layout
Brief: Reduce energy demand without compromising on Compliance
Solution:
• Reduce existing air change rates
• Reduce existing fresh air volume
• Install 2 new VSD’s to the 100kw supply air fans
• Replace the existing supply air diffusers to improve air distribution
• Use existing warehouse HVAC system to serve Retained Sample Store
• Risk based approach to mitigate potential “out of condition” impact
Conclusion: EECO2 supported HVAC design review, project scoped out & local contractors bid to complete project – project let & successfully completed
Site Energy Manager Comments:
“This project was key for delivering the sites 2010 energy target. It exemplifies how the proper air flow & fresh air can contribute significant energy savings. This type of project will be replicated in the remaining areas of our Facility”
Alan Stewart – Site Energy Manager

Wilton Centre
GSK - Argentina
GSK - Singapore
GSK - Tennessee